Vimal, a project manager, made a construction contract with another company which specifies a penalty for delay of completion beyond a certain date as follows: \(₹\)150 for the first day, \(₹\)200 for the second day, \(₹\)250 for the third day, etc., the penalty for each succeeding day being \(₹\)50 more than for the preceding day. How much money Vimal has to pay as penalty, if he has delayed the work by 38 days?
The penalty amount Vimal has to pay is \(₹\)_______