In a company, if a project can be done in 76 days by 23 women, then how long will it take for the project to complete if 8 women left the project? (Find the days using person days method)
 
The time taken to complete the project is  days.
 
(Note: If the answer is a whole number write as it is. If not, round off the answer and write it as a whole number.)